KEEPING TRACK | Update on the StrathAyr track project - Part 4

28 Jun 2023
Auckland Thoroughbred Racing

We’re making good progress with our track project after some less than desirable weather (click here to read Part 1, 2 & 3 of our ‘Keeping Track’ series) and in this edition we will outline the progress made since our last update in February.


A minute with Martin

Click on the video below to hear from Martin Neville, project manager at StrathAyr, who we caught up with in early June so he could give us a glimpse of the various layers before the team completed the sand profile.

 

 


The latest dirt (or rock!)

Our project team provides a progress report on how things are shaping up.

In February this year, we sent out the third of our quarterly updates regarding our track upgrade project. The update included what had been completed since the September update. It is now time to check in and see what has been completed since February.

 

A look at how the Ellerslie track is shaping up.

 

1. What has been done since the last update?

Up until mid-June, the following has been completed:


Underpass

  • The underpass construction is now 95% complete with fencing and landscaping works to be completed. The completion of the underpass is expected in early July

  • Anti-graffiti coating in the underpass has been completed

 

Pond

  • Pond earthworks are now complete with approximately 32,000m3 of earth removed which included 2,500m3 of hard basalt rock

  • Installation of the pond liner and the fencing of the pond has been completed

 

Lining of the new irrigation pond has taken place.

 

Other

  • Main track earthworks have been completed (apart from the construction crossings)

  • Carpark and access road earthworks are now complete

  • 70% of the carpark and access road pavement is now constructed with HEBs focused on sealing the pavements from the beginning of July

  • More than 4000m3 of basalt rock has been excavated and crushed offsite and imported back to be used as subbase for the carpark

  • 99% of ambulance earthworks now complete

  • 97% of main stormwater drainage complete

  • 99% of kerbing in the carpark, access road and underpass complete

  • 97% of services ducting (for power, CCTV, speaker, and other communications)

  • New signage boards have been installed

 

StrathAyr Track Profile

  • The mainline drainage has now been completed with the instalment of the final three catchment mainlines between the track and the pond.

  • Apart from the 60-metre construction crossings, subsoils drains have been installed around the track as well as the gravel laid.

  • All sand has now been delivered (35,000 ton)

  • The sand layer has been completed across 100% of the track

  • Mixing of the strathayr profile (sand/peat/mesh) is complete

  • In regard to the pond, the manifolds are installed ready to connect to the delivery lines with the installation of the pumps

  • Fencing is 75% complete with the remainder to be completed by the middle of July

  • StrathAyr is commencing the toping layer this week with the view to seeding the first section of the track in early July with the final section to be seeded two weeks after

 

2. What’s next to be completed?

  • Carpark and access road pavement construction

  • Ambulance track pavement construction

  • Underpass fencing and landscaping

  • Infield earthworks

  • Offsite rock removal

  • Landscaping around the pond

 

 

3. What’s gone well since the last update?

  • Ensuring the subsoil drainage and gravel layer is laid across the track apart from the construction crossings which ensures the track is now waterproofed – a significant milestone!

 

4. What challenges have been faced since the last update?

  • As expressed in previous editions, the main challenge has been wet weather with nearly all of Auckland’s annual average rainfall reached before the official start of winter (1 June) which thus includes the, traditionally, driest months in January and February.

  • COVID-19 and the resulting absences continue to be a resourcing challenge.

 

Stay tuned for our next update!

Major Partners